Building the Flashline Mars Arctic Research Station on Devon Island
by Robert Zubrin


Lifting a panel into place using a pulley method.
 |
|
The Mars Society took a giant step forward this
summer with the successful construction of the Flashline
Mars Arctic Research Station on Devon Island.
Devon Island, is located circa 75 degrees north in
Canada’s Nunavut Territory. Consisting largely of polar
desert with a 15-mile diameter meteorite impact crater,
the completely uninhabited island is one of the most Mars-like
environments on Earth. Since 1997, NASA scientists
led by Dr. Pascal Lee have been exploring the area in order
to explore Mars by geologic comparison. At its Founding
Convention in 1998, at the suggestion of Dr. Lee, the Mars
Society decided to make the construction of a simulated
human Mars exploration station on Devon Island its first
major project. The purpose of the station would be to
continue the geologic exploration of Devon, but do it in the
same style and under many of the same constraints as would
be involved in conducting such activities on Mars. By doing
so, researchers would be forced to confront some of the
problems of human Mars exploration and begin the process
of developing appropriate field tactics for exploring the
Red Planet.
Starting in the fall of 1998, a volunteer Mars Society
task force was formed to define the project further, and
during 1999 private funds were raised allowing the project
to be initiated in earnest. In January 2000, a contract for
fabrication was let to Infrastructure Composites
International (Infracomp) of
Commerce City Colorado, whose
unique ultrastrong, comparatively
lightweight, and weatherproof
fiberglass honeycomb technology
provided an attractive option for
the Devon Island Station.
Infracomp’s craftsmanship
proved to be excellent. However,
for various reasons, the fabrication
effort fell seriously behind
schedule. This resulted in a crisis
in early June, when it became clear that unless something
was done, the structure would not be ready in time for the
scheduled June 28 shipout. This crisis was overcome
however, by the mobilization of additional labor from Mesa
Fiberglass, Pioneer Astronautics, and volunteers from the
Rocky Mountain Mars Society, some of whom worked up
to 2 weeks in the fiberglass factory with no compensation
in order to get the structure out of the factory on time.
Accordingly, on June 28, three trucks carrying the
components of the Station left Colorado for Moffett Field,
CA, where, together with gear for the NASA-led Haughton
Mars Project, they were loaded on US Marine Corps C-130
aircraft for flight to Resolute Bay in the high Arctic.


Laying out the panels for the hab.
 |
|
The plan was to deliver the station components to
Devon Island via C-130 paradrop, as the large fiberglass
panels comprising the station were much too large to be
brought in by the small Twin-Otter aircraft used for general
transportation between Resolute Bay and Devon Island.
Five paradrop sorties from Resolute to Devon were needed.
The first three paradrops carrying the walls, legs and some
of the dome sections of the habitat occurred on July 5.
These drops were largely successful, in that the payloads
were delivered safely to the ground, but fell wide of the
Haynes Ridge target construction site. The fourth drop, on
July 8, carrying the remaining domes and other equipment,
went well. However, July 8th’s fifth and final drop, was a
disaster. The payload separated from the parachute at an
altitude of 1000 ft, causing the complete destruction of the
habitat fiberglass floors, the
trailer that had been shipped
to the Arctic to enable
movement of the large 800
lb fiberglass panels in the
event they did drop wide of
the target site, and the crane
required by the plan to
construct the station.
With the loss of the
trailer, the floors, and the
crane, the construction crew
that the Mars Society had paid to fly to Devon to assemble
the station declared that building it this year was impossible,
and left the island. At this point, it seemed to most observers
that the project was doomed. Indeed, one journalist covering
the events went so far as to ask me "Dr. Zubrin, do you see
a parallel between the failure of your mission and that of
the Mars Polar Lander?" My reply was "There’s a parallel
in that we both hit a rock. But the difference is that we
have a human crew here, and we are going to find a way
out of this."
Refusing to give up, Pascal and I assembled a new
makeshift construction team consisting of a combination
of Mars Society scientist-volunteers, Inuit youth hired from
Resolute Bay, and journalists, who, having come to cover
the construction of the station, were strongly encouraged
to participate in the effort. Frank Schubert, a general
construction contractor from Denver and Founding
Member of the Mars Society was brought in to direct the
construction effort, with
the assistance of his
foreman Matt Smola, and
Infracomp president John
Kunz. A new trailer, "the
Kunzmobile" was
constructed out of wood
and parts of a wrecked
baggage cart from
Resolute Bay airport, and
using it, the team managed
in three days of heavy
sledding in freezing rain to
move all the mistargetted
habitat components to the
construction site. Wooden
floors to replace the ruined
fiberglass decks were
designed, and materials for their construction were secured
in Resolute Bay. To replace the crane, an alternative ancient-Roman
style construction technique was devised, utilizing
large labor teams with bracing timbers and guy ropes
operating in coordination with a scaffold and a winch to
lift the 20 ft by 7 ft 800 lb wall panels into place. Shortly
before the wall-erection effort was to begin, the weather
cleared, and the team seized the opportunity to get the job
done fast in good weather by instituting 14-hour work-days.
In three days, the walls were up. The decks were
then partly built out, and then block and tackle gear was
used to haul the 350 lb dome sections up onto the upper
deck. Once there, a scaffold was constructed, and two dome
sections plus the central core were erected to create an
arch. The dome sections were then added in, with the last
one being brought into place around 7 pm July 26. Interior
buildout then commenced rapidly.
On the evening of July 27, I sent a message to the
Mars Society Mission Control in Denver to establish contact
in preparation for the commencement of simulation
operations the next day. "Mission Control, this is Flashline
Station. Are you there? Please Respond." Mission Control
replied;
"Flashline Station, this is Mission Control. It’s good
to hear from you.
"Clearly, failure was not an option."
In a ceremony attended by about 50 scientists, Inuits
and journalists on the evening of July 28, the station was
formally commissioned. Speeches were given by NASA
Ames scientist Carol Stoker, British Antarctic Survey
scientist Charles Cockell, Pascal Lee, and myself. At the
conclusion of my speech, a shotgun was fired in salute to
the red, green, and blue Martian tricolor flag flying atop
the station. I was then given a bottle of champagne, which
was smashed against the habitat to christen it. This
provoked a sigh from the
crowd. Pascal, however,
immediately reassured
them; "It’s all right folks.
It’s just Canadian
champagne."
The first crew,
consisting of Pascal Lee,
Mars Society webmaster
Marc Boucher, Frank
Schubert, the Discovery
Channel’s Bob Nesson,
and I then entered the
habitat for a largely
symbolic one night and
one day occupation and
simulation. A more
thorough four-day
shakedown simulation was begun on July 30. Commanded
by Carol Stoker, the crew of the shakedown consisted of
Stoker, Marc Boucher, NASA Ames’ Bill Clancey and
Larry Lemke, the University of Toronto’s Darlene Lim,
and Bob Nesson. In the course of the next several days,
this group lived and worked in the hab, supporting a series
of exploration traverses on Devon Island and the field
testing of a Hamilton Sundstrand Mars spacesuit prototype.
To report of their activities, the crew engaged in Mars-earth
simulated time-delayed dialogue with Mission Control
in Denver.
On August 4th, simulation operations were
discontinued. The hab was then sealed for the winter. Based
on experience gathered to date, plans are now being
developed for the summer of 2001, when the station will
be used to support 8 weeks of Mars operations field
research in the high arctic.
Everything did not go right on Devon Island. Neither,
however, can we expect everything to go right on the first
human mission to Mars. The military has a saying; "All
plans fail upon contact with the enemy." In the wild Arctic,
all plans fail on contact with reality. The same will be even
more true on Mars. When venturing into the unknown, the
unexpected will happen. But what we proved on Devon
Island, is that a resourceful crew can deal with it.
On the piloted Mars mission, the human crew will
be the strongest link in the chain.
|
 |
|